Hyperscaler partner for data center could be announced soon

GEOFFREY WOEHLK/THE FORUM
Nodaway County Administration Center building

MARYVILLE, Mo. — Scale Microgrids could be close to announcing the company that would operate the White Cloud Acres hyperscale data center, a county commissioner said Tuesday.

Slated to be built about 8 miles south of Maryville along U.S. Highway 71, Scale has been developing the $6.3 billion data center and associated natural gas power plant project since late last year. Company representatives have consistently said that Scale aims to sell or lease the data center portion of the project to a hyperscale operator before construction begins. Although Scale primarily builds and operates power plants, the explosion of data center development has created a ripe opportunity for power plant developers to branch out into data centers because of those facilities’ massive power needs. Scale would operate the co-located power plant at White Cloud Acres.

In June, Scale unveiled a project timeline that would see construction begin in early 2027. At the time, Dan Scheffler, vice president of development at Scale, said the company did not yet have an agreement in place for a company to operate the data center, but said Scale was expecting to bring in a “Fortune 10” company. AI hyperscalers in the Fortune 10 include Alphabet (Google’s parent company), Apple and Microsoft.

WHAT IS A HYPERSCALE AI DATA CENTER?

An AI data center uses large numbers of processors in one location to complete the intensive computing tasks necessary for AI applications. When you do a Google search, for example, racks of processors at an AI data center work to compile the AI summary that pops up. The more processors, the more summaries can be delivered at a faster pace. A hyperscale AI data center is a particularly massive facility with thousands and thousands of processing units.

While Scale has laid the groundwork for the facility, the eventual hyperscale partner would run the data center, either by purchasing it or by leasing it from Scale. Getting a partner on board quickly could prove crucial to the project’s timeline — the county commission imposed a moratorium on data center development in July, preventing any company from beginning construction on a data center project.

To lift the moratorium, the county is looking for more specific answers to questions about potential harmful effects of the data center, including sound and air pollution, water and power use, and more. Scale has provided some information so far, the commissioners have said, but some answers may change once the end user gets involved.

During Tuesday’s regular county commission meeting, North District Commissioner Chris Burns clarified that as far as he knows, Scale is still the developer of the project. But that could change soon.

“And I think they’re getting close, from what I’ve heard, as far as announcing that,” he said. “So Scale is still developing the project and the power plant. There could be changes to the development of the data center depending on who the hyperscaler is, is what we’ve been told.”

Josh McKim, executive director of Nodaway County Economic Development, and Dustin Skoglund, superintendent of the South Nodaway R-IV School District, said that was their understanding as well.

In July, the county received a first draft of a proposed development agreement from Scale that has so far proven to be a nonstarter, though the commission has not shared details of the proposal publicly. In general, a development agreement will outline tax abatements and performance expectations, like employment requirements and emissions limits. Although Scale has begun negotiating that agreement, it’s the eventual data center operator that would take it on in whatever purchase or lease contract the company signs with Scale. If the company gets publicly involved soon, then it could have a larger role in actually developing the agreement. McKim said it’s not unusual for major projects to take either approach.

“(A) developer, it’s not uncommon for them to build out a good portion of that development agreement before it’s handed over to the end user,” he said. “It’s common practice, and there’s a lot of money to be made as a developer doing that, because that’s a headache that a lot of big companies — they don’t want to deal with it.”

Other data center notes

  • McKim said he has been tracking land sale announcements in the county and hasn’t seen any go through yet in the area of the White Cloud Acres project. Scale came to conditional agreements with landowners in the area, but has not actually purchased the land yet. When that happens, it will likely indicate the project is prepping to move toward construction.
  • McKim also said he has had no more meetings with two companies that in late July expressed interest in developing smaller data center projects in the county. But he stressed that they remain interested. Amy Ziegler, the chief public relations officer at United Electric Cooperative, added that in the 11-county northwest Missouri region it serves, the company is “slammed” with interest from potential data center developers at least “twice a week.”