MARYVILLE, Mo. — HDR Engineering will produce an analysis of the city of Maryville’s wastewater treatment capacity to help city officials make decisions about requests from potential large users like data centers and power plants.

The $9,780 agreement approved during the council’s regular meeting on Monday charges HDR with reviewing three years of wastewater treatment plant operating data, water production and finished water quality information, potential water and wastewater demands from large users, and the city’s existing long-term demand projections. HDR will also coordinate with the Missouri Department of Natural Resources to evaluate regulatory requirements associated with the potential reuse of treated wastewater and any changes that may be required to related city permits. City Manager Ryan Heiland said that as part of the regulatory review process, HDR would analyze the downstream effects of more potential wastewater discharges into the One Hundred and Two River.

The result will be a two-page memorandum summarizing the findings and making a recommendation on what factors the city should consider when looking at requests from large users.

The council requested the analysis after Nodaway County Public Water Supply District No. 1 released an independent feasibility study in June that analyzed water resources available for the White Cloud Acres data center project and its accompanying natural gas power plant. The study recommended that the most efficient solution would be for the data center to use recycled wastewater from the city of Maryville to cool its equipment, and then send that wastewater back to the city for disposal at the wastewater treatment plant.

But the study left some questions unanswered about how much water the facilities would require, and acknowledged that more discussion and coordination among the water district, the city and the data center developer would be necessary before moving forward.

Council members at the time authorized city staff to engage longtime consultants HDR to produce another that would be tailored to the city’s needs and give them a better idea of the short-term and long-term effects on the city’s water resources.

The report should be completed and returned to the council in about a month, Heiland said.

Other City Council notes

  • In his annual report to the council, Josh McKim, executive director of Nodaway County Economic Development, said that the organization has found particular success with loans to small businesses and is working to acquire funding to provide more zero-interest loans in the future as part of a revolving fund. He said the top priorities for local industries remain housing and child care.
  • The council approved next year’s tax levy at $1.0892 per $100 assessed valuation, an increase of $0.0091 from last year. The increase was solely in the debt service levy.
  • Council members approved a $10,607.72 agreement with Next Generation Recreation to replace the swing set at Happy Hollow Park. The Maryville Parks and Recreation board approved the agreement last week, but the council needed to approve it as well because of the amount of the expenditure.
  • The council’s next regular meeting will be held on Sept. 8 rather than Sept. 14 because of staff and council scheduling conflicts. The council may also look to move a budget work session that had tentatively been scheduled for Sept. 21.