ST. JOSEPH, Mo. — The Missouri Department of Transportation has contracted Above & Below Contracting for a resurfacing project that will lengthen the lifespan of roadways in three counties.

According to a news release from MoDOT, the project is scheduled to begin Thursday, Sept. 4. The contractor’s tentative schedule is as follows:

  • Sept. 4 – Nodaway County Route JJ
  • Sept. 6 – Nodaway County Route NN
  • Sept. 13 – Nodaway County Route AB
  • Sept. 16 – Nodaway County Route WW .
  • Sept. 22 – Nodaway County Route AH
  • Sept. 29 – Nodaway/Andrew counties Route N
  • Oct. 3 – Nodaway/Andrew counties Route Y
  • Oct. 10 – Holt County Route C

During resurfacing, each route may be closed in up to two-mile sections. Motorists will need to seek an alternate route during the closures.

All routes are anticipated to be complete by mid-October 2025.

All work is weather permitting and could be rescheduled, noted the release.

Project schedule updates will be provided on the Traveler Information Map, located online at traveler.modot.org/map.

MoDOT asks drivers to “work with us” by always buckling up, keeping phones down, slowing down and moving over in work zones.

Get project and work zone news straight to email by signing up for eUpdates. Information is also available 24/7 by calling 888-ASK-MODOT (275-6636) or by visiting modot.org/northwest.

Leave a Comment