Path to South Main Phase II runs through 2025

SK DESIGN GROUP
Phase II of the South Main Corridor Improvement Project will include a landscaped, raised median between Larry Lane and Horsepower Drive, as seen in this early preliminary rendering from 2014.
The Maryville Forum’s annual Progress Edition is a special section that highlights what our community has accomplished in the previous year and what we can look forward to in the next.
MARYVILLE, Mo. — Four years after work began on one of the most impactful infrastructure projects in Maryville’s history, the South Main Corridor Improvement Project will kick into high gear in 2025 with an eye toward completion in early 2026.
Phase I of the infrastructure overhaul, which addressed the section of South Main Street from the intersection with South Avenue to the intersection with State Highway V, was completed in September 2023. It made a host of functional and aesthetic improvements designed to make the corridor safer, more accessible for pedestrians and more of a welcoming sight for visitors driving down Maryville’s most significant economic thoroughfare.
SOUTH MAIN PROJECT TIMELINE
- Dec. 2012: Master plan cites South Main as No. 1 priority
- Aug. 2015: Traffic corridor study outlines problems, solutions
- April 2017: Capital improvement sales tax extended, providing funding for a decade-long construction plan
- Dec. 2018: $10.48 million BUILD grant awarded for project
- Dec. 2019: Full corridor design completed
- April 2021: Project split into two phases after bids come in over budget
- Oct. 2021: Phase I begins construction
- Aug. 2022: $5.9 million RAISE grant awarded for Phase II
- Aug. 2023: Phase II bids come in over budget
- Sept. 2023: Phase I completed
- Nov. 2023: $500K TAP grant awarded for Phase II trails
- Aug. 2024: Phase II begins construction
A year later, crews broke ground in September 2024 on Phase II, which is making the same types of improvements — including traffic and pedestrian safety additions, drainage improvements and aesthetic enhancements like lighting — on the stretch running from the intersection with State Highway V to U.S. Highway 71.
When the new roadway is opened, it will mark the culmination of more than a decade of planning that began in December 2012 with a goal in the city’s comprehensive plan.
Laying the groundwork
By 2015, the city had a traffic study in hand that outlined the problems on the clogged corridor, and prescribed fixes. The estimated price tag? Between $12 and $15 million.
To pay for it, city voters endorsed an extension of the capital improvement sales tax in 2017, setting the city on its path toward a plan of at least a decade of construction to complete the improvements — all on the dime of local taxpayers.
But in late summer 2018, the city worked feverishly with the Northwest Missouri Regional Council of Governments to complete an application package for a federal Better Utilizing Investments to Leverage Development (BUILD) grant. City and NWMRCOG staff worked around the clock in a 45-day sprint to submit the materials, and sent in the application with “minutes to spare,” according to City Manager Greg McDanel.
Even after the application had been submitted, the project still faced long odds: the BUILD program had $1.5 billion of funding to allocate for 851 potential projects requesting more than $11 billion of aid from across the country.
In the end, the $10.48 million BUILD grant awarded to Maryville, one of only four in Missouri that year, would prove to be a turning point for the city’s confidence in its grant process and ability to secure federal and state funding.
It also meant a much quicker timeline of only a few years, and a local match of only a few million.
But just before the project was ready to get into full swing, the COVID-19 pandemic struck, throwing a wrench into the well-laid plans.
Delay after delay at the federal level pushed the process back into 2021, when the city finally received the first construction bids for the project that had been gestating since 2012 — and they were way over budget.
Driven up by pandemic-related issues affecting global supply chains, what had been estimated as a $12-13 million project in 2018 was, by March 2021, now estimated to be closer to $16 million. And that number would only go up.
The solution drawn up by city staff and contractor SK Design was to split the project into two parts that are now known as Phase I and Phase II.
Overcoming roadblocks
While Phase I was underway, city officials went to work on securing funding for Phase II. Key to that was a $5.925 million federal grant through the U.S. Department of Transportation’s Rebuilding American Infrastructure with Sustainability and Equity (RAISE) program, the successor to the BUILD program that had funded Phase I. When that grant was awarded in August 2022, requiring no local match, the nearly $6 million was enough to cover the cost of the remaining project.
But, a year later, when the city received only one bid for the project that was about $4 million higher than had been estimated, city staff had to overcome yet another obstacle.
Scaling it started with securing another grant, a $500,000 Transportation Alternatives Program grant from the Missouri Department of Transportation. That grant paid for a little over half the cost of the sidewalks included as part of Phase II that will run along South Main.
Additionally, the city pared down Phase II’s scope, scrapping plans to move overhead utility lines underground like had been done in Phase I, reducing the cost by an estimated $1.4 million. That component could be added back in as the project goes along if funding is available. All told, Phase II’s price tag came in at a little over $8 million. Also, the city authorized $1.7 million in bonds for the project.
In June of last year, the City Council approved a new bid from Genesis Environmental Solutions for Phase II, and the 18-month clock on construction began on Aug. 19, 2024.

FORUM FILE PHOTO
Phase II of the South Main Corridor Improvement Project will run from the intersection with State Highway V to U.S. Highway 71, and is anticipated to be completed in early 2026.

FORUM FILE PHOTO
The second phase of the South Main Corridor Improvement Project got underway in August 2024 and is primarily funded by a nearly $6 million federal RAISE grant.