Skidmore opens bids for lead line inventory

FORUM FILE PHOTO
Skidmore City Hall
SKIDMORE, Mo. — The Skidmore Board of Aldermen opened 10 bids during its June 13 meeting from plumbing and water repair companies throughout the country for the city’s lead service line inventory.
The inventory is required by the U.S. Environmental Protection Agency and the city is being assisted in the process by the Missouri Department of Natural Resources.
According to Missouri DNR, each water system is required to submit an initial inventory to the department on or before Oct. 16.
As the local water provider, the city is working under a strict deadline to complete the project, about which there is still some confusion.
During the meeting, City Clerk Sadie McHugh told the board this was just for the preliminary inventory of the lines and not the entirety of the work to repair. She said this is what DNR told her.
Upon looking briefly at the bids, Mayor Teresa Carter said these bids include the work to repair the lead lines.
Carter said as part of the bids, she saw in the documents a section for “replacement plan services,” which she said provides a per-resident price based on the 142 connections the city services.
“We’re on a very strict time period,” Carter said. “So we need to decide which company we wanna go with.”
The board agreed some review of the bids was warranted. They met again on June 20 to review the bids again. Look for this week’s newspaper on Thursday for more information on that meeting.
The bids received include the following:
- Better By Design; Brookfield, Missouri – $76,850
- Byrne & Jones Construction; St. Louis – $56,184
- Environmental Works; East Carondelet, Illinois – $79,129
- Goins Enterprises; Joplin, Missouri – $93,100
- HBK Engineering; Chicago, Illinois – $100,687
- Perry Plumbing Services; Rock Port, Missouri – $98,560
- Recon Utility Services; Bohemia, New York – $111,690
- Schulte Supply; St. Peters, Missouri – $68,305.80
- Total H20 Solutions; Wappapello, Missouri – $94,690
- Z&R Trenching; La Belle, Missouri – $52,576
Red tags
After quite a bit of discussion, the board agreed that McHugh and City Maintenance Supervisor Mike Reasoner should hang red tags and then shut off the water for customers who have not paid, according to the city ordinance.
McHugh said the city has several habitual late payment-makers causing more work for the city. She brought to the board the idea of an extra $10 fee for a red hangtag placement. She said Valerie Mains with Missouri Rural Water suggested the fee.
Alderman Tim Slagle disagreed with the idea of charging more for work he considered within the regular parameters for the city.
“Used to be, we didn’t give any grace period,” he said.
He said there are a lot of stories that people have run into difficulty paying bills. He explained that he had one himself after being in the hospital and not working.
“At some point, you know, you have to draw the line,” he said.
The city will no longer give a grace period and plans to hang red tags with water shutoffs according to the city ordinance.
Other news
- Alderman Dennis Gladman will be taking on the city’s code enforcer position.
- Carter told the board that the work that SMICO was doing to repair the leaking pipe that crosses a creek in town has been completed, but doesn’t have supports, which she believed to be listed in the work to be completed. She said the city would check to make sure everything was completed as bid. “I’m just glad to have it done,” Alderman Steve Day said.
- The board agreed to use their own tablets and not purchase any for use during the city meetings. McHugh had suggested the option two months ago as a way to save on print and ink costs.
- McHugh is working with Valerie Mains of Missouri Rural Water to create the city’s annual budget.
- Board members approved the purchase of a new air conditioner for City Hall, should the current one prove to not work better upon repair and cleaning. The board approved Mayor Carter to spend up to $500 on a new unit should it be warranted.
- Alderman Tim Slagle is donating materials and his time to create small concrete boxes to mark and hold flagpoles at Hillcrest Cemetery.
- Other cemetery business includes the board agreeing that City Maintenance Supervisor Mike Reasoner is allowed to pick up flowers that are blown off of headstones in order to complete mowing of the cemetery.
- The city plans to look into the cost of painting a “skim coat” on the bricks around the new door that don’t match the rest of the building. A cost estimate meeting was between $150 and $200.
- McHugh informed the board and audience that the city will now charge $12 to the public for copies of the paper packet presented to board members at meetings. The city will provide packets electronically at no cost, when requested. The city will still furnish agendas free of charge. McHugh said it is a time issue, but also noted that it will help save money on printing and paper costs.
- Carter read a list of properties that the city would like to see demolished. The city has been working with the Northwest Missouri Regional Council of Governments seeking funds to help property owners, business and residential, with the cost of demolition. She noted that many people around town have been working to clean up their properties and she thanked them for it.
- The city received a $15,000 matching grant from the Gladys M. Rickard Charitable Trust for the purchase of playground equipment. The equipment that the city has looked into, Reasoner said, costs $30,000 to be delivered and installed. Carter said the city would be on the lookout for ways to raise funds to match the grant.
- Resident Bob Saxton spoke with the board about the roadwork being done near his home on Locust Street. He noted that it’s been a while since roadwork has been done and he wondered about how the road would be left following the work. As it stood during the meeting, he didn’t believe he could manage the upkeep. He believed that residents should be notified when the city planned to do work on the roads. Reasoner explained he wasn’t finished with the road and that he’s already spoken to residents, many of whom were angry the work was happening at all or wanted it in a different way. Reasoner said he has a lot of gravel roads to crown during the summer.