Skip to content

Highway 46 reopens after bridges replaced

SKYE POURNAZARI/THE FORUM
The recently completed Stream and Florida Creek bridges are shown west of Maryville on State Highway 46. These two bridges had been one-lane before their replacement — part of Gov. Mike Parson’s Focus on Bridges program.

MARYVILLE, Mo. — Crews reopened State Highway 46 to traffic on Nov. 12 after the replacement of four bridges about 3 miles west of Maryville.

A part of Gov. Mike Parson’s $351 million Focus on Bridges program, the Missouri Department of Transportation project not only replaced the bridges, but also widened two of them from single-lane to 24-foot, two-lane crossings.

According to Resident Engineer Larry Jacobson the project completion date was originally set for Dec. 1, but thanks to scheduling help from surrounding landowners crews were able to jump to the Florida Creek and Big Slough Creek bridges a little quicker than expected.

“Boone Construction (Co. of Columbia, Missouri) they’re a pretty seasoned bridge contractor and they do quite a few bridges every year across the state,” he said. “They have multiple supervisors. … That’s how they were able to get them done a lot faster.”

He said the company had three of four different supervised crews out at the site at any given time during the project. He said three crews worked on the four bridges while a fourth dirt crew worked on sloping the ground surrounding all four creeks.

Two bridges on the west side of State Route AB were completed first in late October and reopened to local traffic.

Jacobson said there weren’t too many setbacks, and that the longest one only took a couple of days to work through.

While digging out for the Big Slough Creek Bridge, crews discovered an old wall he estimated from the 1930s, about 10 feet deep. He said they spent a day knocking it over.

“We had a couple obstructions when we went to drive piling, but it took an extra couple days, but nothing major,” he said.

Other than that, he said it’s been a pretty standard project.

Total cost of the project was originally awarded at $2,795,788, but because the site was different, Jacobson said they were able to come in under that. He didn’t have an exact amount at the time of this story.

“We try to look at the best way, once we’re on a site, to do work and if we can coordinate it we can maybe save some money in it too,” Jacobson said.

The Focus on Bridges program is set to repair or replace 250 bridges across the state.

SKYE POURNAZARI/THE FORUM
White Cloud Creek is shown last week after the Missouri Department of Transportation reopened State Highway 46 west of Maryville. Since July, the highway has been closed during a four-bridge-replacement project that was completed just last week.

FORUM FILE PHOTO
Steel rebar can easily be seen on the White Cloud Creek bridge in 2019. The Missouri Department of Transportation has completed the replacement of this and three other bridges on State Highway 46 west of Maryville.

SKYE POURNAZARI/THE FORUM
Big Slough Creek bridge is shown last week after State Highway 46 was reopened. The Missouri Department of Transportation had closed several miles of the highway in July for a four-bridge-replacement project that was completed just last week.

FORUM FILE PHOTO
A truck passes over the bridge on Big Slough Creek in 2019. The bridge has been replaced by the Missouri Department of Transportation as part of Gov. Mike Parson’s statewide infrastructure improvement plan.

SKYE POURNAZARI/THE FORUM
The Florida Creek bridge is shown after State Highway 46 was reopened to traffic last week. Since July the roadway had been closed for the four-bridge-replacement project.

FORUM FORUM FILE PHOTO
The Florida Creek bridge is shown in 2019, before being replaced during the Missouri Department of Transportation project by Boone Construction Co. of Columbia, Missouri. The project replaced four bridges on State Highway 46 as part of Gov. Mike Parson’s Focus on Bridges program.

SKYE POURNAZARI/THE FORUM
A truck passes over the Stream Creek bridge on State Highway 46 on Friday west of Maryville. The four-bridge-replacement project has been completed and the roadway that has been closed since July is now open to traffic.

FORUM FILE PHOTO
The Stream Creek bridge is shown in 2019. The bridge has been replaced by Boone Construction Co. crews as part of Gov. Mike Parson’s $351 million Focus on Bridges program with the Missouri Department of Transportation.

Leave a Comment