Mozingo center enters final weeks of construction

in the news

Originally expected to wrap things up by Thanksgiving, crews working on the new conference center and golf course clubhouse under construction at Mozingo Lake Recreation Park will likely miss that deadline by about three weeks, City Manager Greg McDanel said Tuesday.

McDanel said there is no single reason for the delay other than the “delicate dance” of tasks required to finish the interior with paint, carpeting, flooring and drop ceilings, chores that often have to be performed in a certain order so as to accommodate installation of fixtures and furnishings.

Restroom floors, for example, must be installed before restroom toilets, and any delays affecting the first job necessarily set back the second.

Similar factors delaying progress at the center have included the onset of cooler weather, which required the installation of heating units. Without heat, McDanel said, fresh paint would not have dried correctly, and so the start of painting was pushed back a couple of days while the furnaces were hooked up.

Also affecting the work schedule is the Thanksgiving holiday itself, which McDanel said will likely delay completion of flooring and carpeting installation scheduled to get underway next week.

But while the date for finishing the $4.7 million center has slipped, McDanel said the facility should be ready in ample time to host its first major event, a Jan. 6 wedding with a guest list of more than 300 people.

The new deadline for substantial completion, he said, is Friday, Dec. 15, when about 100 municipal staffers are expected to gather in the center’s upper-level banquet hall for the city’s annual employee appreciation dinner.

A second gathering, a Christmas party for employees of a local business, is also scheduled during the last part of December.

McDanel said both events will serve as “trial runs” for center facilities along with operations associated with set-up, tear-down and cleanup.

While missing deadlines is never a good thing, McDanel said a two- or three-week slip in completing the conference center won’t make much difference.

“With a $5 million project, a couple of weeks’ delay is just natural,” he said.

Along with painting, all flooring and carpeting at the center should be installed by Dec. 4. And while the building’s exterior is essentially complete, crews are still working to finish concrete aprons and walkways serving both the upper- and lower-level entries.

But while the final phase of construction appears on track for facility completion next month, still up in the air is a proposed deal with a third-party restaurant operator and caterer.

Located on the lower level, the privately run restaurant is to be one of the center’s main amenities. However, while the city has been in discussions with a dining services vendor for some time, McDanel said a lease has yet to be signed.

McDanel said two vendors sought the restaurant/catering contract, and that a preferred offer was selected by the City Council during a recent closed session. But details of the lease are still being ironed out.

“We’re waiting until the lease is executed to make an announcement,” McDanel said, “and there should be movement on that really soon.”

As for already-scheduled events, those signed up to use the facility can contract with any of a number of approved local catering operations.

McDanel said a total of about 75 events — everything from weddings to corporate retreats to golf tournaments — have been booked at the center for 2018, among them the annual SSM Health St. Francis Hospital Gala traditionally held in February at the Maryville Community Center.

Other work associated with the new facility is to include construction of 20-foot by 20-foot brick “monument” sign directing traffic toward the center and neighboring Boulders Inn & Suites hotel from the intersection of Highway 136 and Liberty Road, the main entrance into the park.

McDanel said work on the sign, to be built by conference center general contractor E.L. Crawford Construction, should begin within 30 to 45 days.