Skidmore seeks options for aging sewage plant

In the News
Decision time is nearing for the Skidmore City Council, which will soon have to decide whether to fix or replace its aging sewage treatment plant.
According to Paul Owings, a Snyder & Associates engineer who is helping the city review its options before he completes a report for submission to the Missouri Department of Natural Resources, the current plant operates inconsistently, which means the small west Nodaway County community is sometimes out of compliance with state environmental standards.
Owings said last week that the city has essentially three options: construction of a modern mechanical plant, switching to an “application” treatment system based on spreading pre-treated effluent and biosolids over a large tract of land, or repairing and updating its existing facility.
The cost of bringing Skidmore’s wastewater treatment processes into compliance won’t be cheap, and reportedly could cost as much as $3 million if the city decides to build a new plant.
While no decision has been made, Skidmore Mayor Tracy Shewey said the council is leaning toward repairing and upgrading the existing plant, which is based on a “trickling filter” system, technology that has been the workhorse of municipal water treatment for more than a century.
In a trickling filter system, pre-settled wastewater, meaning sewage with the solids removed via a clarifying tank, is continuously ‘trickled’ or sprayed over a thick layer of rocks or other media.
As the water migrates through gaps in the rock filter, organic pollutants are aerobically degraded by a microorganism-rich biofilm.
In Skidmore, Shewey said, the main problem is that the rotating sprayer that trickles effluent into the filter doesn’t always work.
In addition to repairing the sprayer, Shewey said upgrading the existing facility would likely entail adding bacteria-killing ultraviolet lights and a chlorine treatment system
While all options are still on the table, the mayor said she thinks an upgrade rather than construction of a new facility will end up as the favored choice. But whatever path the city chooses, Skidmore residents are going to have to pay more for sewer service.
Shewey said the council, which in January raised wastewater treatment rates from $15.50 to $18 for the first 1,500 gallons of effluent plus an additional 50 cents for every 1,000 gallons after 2,500, will likely implement future increases incrementally in an attempt to ease the burden on ratepayers as much as possible.
She added that voters will probably be asked to approve a bond issue, proceeds from which will be used to finance the upgrade.
Typically with such projects, bond yields pay for the facility while user rates are used to service the debt.
The additional revenue will also be needed to fix inflow and infiltration issues caused by leaky pipes that allow rainwater to enter the sanitary sewer system. Such leaks raise costs by forcing the plant to treat more gallons than is necessary.
In addition to raising rates and assuming debt, Shewey said the city is also looking into the possibility of government grants and low-interest loans.
For the time being, at any rate, Skidmore isn’t facing a DNR deadline for fixing the problem or the threat of punitive fines, though such measures are possible if the town continues to pump out-of-compliance effluent into the Nodaway River.
“I think as long as we keep in contact (with DNR) and keep making headway, that isn’t a problem,” Shewey said. “But we have got to keep moving forward.”
The mayor added that the next step will be for the council to make a decision with regard to upgrading or replacing the existing plant so that Owings can complete his report and submit it to state officials.