Wet weather delays runway construction

TONY BROWN/DAILY FORUM
Large mounds of gravel, consisting of ground-up fragments of the old runway at Northwest Missouri Regional Airport, line the substrate of the new runway being built by Ideker Construction of St. Joseph. Work on the landing strip has been delayed by wet weather and is now scheduled for completion sometime in mid to late October.

Unseasonably wet weather over the summer will delay the reopening of Northwest Missouri Regional Airport, a city-owned airstrip, terminal, fueling dock, and hangar complex located on Highway 46 just west of town.

The airport has been closed since mid-June when crews from Ideker Construction in St. Joseph began breaking up most of its 4,600-foot concrete runway, which has been smashed into gravel that will be used as a base for a new landing strip.

Not included in the rebuild is the southernmost 600 feet of the runway, which was added as an extension in 2008 along with a second taxiway.

The remainder of the 75-foot-wide strip, all of which is slated for replacement, was built in the mid-1990s.

Assistant City Manager Ryan Heiland, the city’s lead administrator for airport facilities and operations, said Wednesday that the airport’s original Oct. 5 opening date has been pushed back to mid to late October. He added that, barring some major, unforeseen difficulty, there is no reason why the project shouldn’t be completed during the current construction season.

As things stand now, the old runway has been completely removed, and the gravel into which it was ground stands in large piles along both sides of a smooth, razor-straight substrate.

Workers are spreading heavy, black fabric over the substrate, which Heiland said will be covered in turn by the gravel and ultimately concrete.

When all the prep work is completed, a massive concrete pour is expected to take several days, Heiland said.

In order to facilitate construction, Ideker has erected what amounts to a cement manufacturing plant at the airport, the tower of which is visible north of the terminal building and east of the runway.

Total project cost of the runway rehab is just under $3.4 million, with more than 90 percent of the funding coming from a Federal Aviation Administration Airport Improvement Program grant.

The city is responsible for a $339,000 local match, which is being financed using a Missouri Department of Transportation Statewide Transportation Assistance Revolving Fund loan — a program known as STAR.

Authorized by the Missouri General Assembly, STAR was created specifically to provide low-interest loans to local governments for non-highway projects such as railroads, waterways, and air travel infrastructure.

Maryville’s loan is to be paid back over 10 years at an interest rate of just under 2 percent.

City officials are currently seeking an additional $1 million FAA grant to re-pave the airport’s “apron,” essentially a parking lot for airplanes that adjoins the facility’s general aviation and jet fuel island.

The apron grant, which has not been awarded but is included as a line item in the proposed fiscal 2017 budget, would also require a local match of around 10 percent, which City Manager Greg McDanel said would likely be funded using a STAR loan as well.

Getting the two-decade-old portion of the runway replaced has been a priority for the city for a number of years as increasingly frequent repairs became necessary due to cracked and buckled pavement, which had become particularly susceptible to hot weather.

Things had gotten to the point, according to Heiland, that pilots of small jets were sometimes radioing ahead before landing at Maryville and requesting that the runway be swept, fearing that small chunks of loose pavement would damage their aircraft.

Other issues being addressed during the current construction period include installation of new approach lights. The lights formerly stood at different heights and thus created a potential hazard during night landings. In addition, the lights, which were activated via air-to-ground radio signals, sometimes failed to come on altogether.

In addition to work by Ideker crews, an electric subcontractor was on site this week installing the new approach light system.

Other ongoing work includes repaving of the northernmost of two connecting taxiways and installation of a new wind cone.

While the airport doesn’t get a lot of publicity, upgrades at the facility have been progressing steadily for some time, and McDanel has suggested the city might want to consider some sort of marketing or branding effort to increase awareness about the facility once the reconstructed runway is complete.

Improvements during recent years include a terminal building completed in 2007 and equipped with a weather station and pilots’ lounge and installation in 2009 of the two-tank fuel island.

TONY BROWN/DAILY FORUM
Ideker Construction workers use heavy machinery to spread gravel over black fabric rolled across the substrate of the runway at Northwest Missouri Regional Airport. The gravel will in turn be covered by poured concrete in order to form a new landing surface 4,600 feet long and 75 feet wide.

TONY BROWN/DAILY FORUM
In order to expedite construction of the new runway at Northwest Missouri Regional Airport, general contractor Ideker Construction has installed what amounts to a small cement plant on site. The plant is located north of the airport terminal and just west of the Nodaway County Community Building.