Performing arts center nears completion, gym construction begins

By JENNIFER DITLEVSON HAGLUND Staff writer
In the foyer of the performing arts center, workers prepare a wall to install a stone effice. The box office and theater will be ready for shows this fall semester.
As one building project in the Maryville R-II School District draws closer to its end, another begins.
The construction of the performing arts center at Maryville High School continues on schedule, and it should be ready for use at the beginning of the upcoming school year. Last week workers began installing seats, and this week they began applying a stone effice in the foyer.
In addition to using the performing arts center for plays and ceremonies, the district will use the space for testing, instruction, and professional development. The first seven rows of seats are equipped with pullout desk panels so students and faculty can take notes when necessary.
With the performing arts center expected to open soon, Maryville School District Superintendent Becky Albrecht said at the June board meeting that people had called already asking for information about renting the space. In updating the policies and fees for building use at the meeting, Albrecht and Assistant Superintendent Steve Klotz recommended that the board approve the new fee schedule for the performing arts center.
For four or fewer hours, rental of the building will cost $125, with each additional hour costing $25. A custodial charge of $50 would also be added to that. There will be a $300 advance refundable deposit.
At its June meeting, the school district’s board of directors also added a part-time position in the supplemental activity schedule to manage the new performing arts center.
In the job description, the person holding the job would manage the facility schedule as well as operate the lights and sound. Any time sound or lighting is required for a major production, the person in this position must be in attendance. The starting pay for the position would be approximately $25 per hour.
In connection with the other construction project, Klotz said he expects that in a week to 10 days, the footings of the FEMA structure will be poured, and soon after, the die-cast panels will be set. The process of erecting the structure will take up to three weeks.
The building will double as an auxiliary gymnasium with three rows of bleachers.
Although the contract that began in May 2016 allows for 365 days to complete the project, Klotz said that it is now expected be finished in March or April.
Through value engineering, the district saved $183,000 with the performing arts center last fall, but Albrecht recommended, and the board approved, that $33,640 of those reserved funds be spent on preparing electrical and sewer hookups in the green rooms at the theater. The rooms will not be finished, but ready for the district’s maintenance crew to complete at a later date.

By JENNIFER DITLEVSON HAGLUND Staff writer
Workers unpack and installed nearly 700 seats at the new performing arts center at Maryville High School to prepare for the theater’s opening at the beginning of the upcoming school year.

By JENNIFER DITLEVSON HAGLUND Staff writer
Construction remains on schedule and the stage is on the way to completion, but the curtains will not be installed until the dust settles.

By JENNIFER DITLEVSON HAGLUND Staff writer
Maryville R-II Assistant Superintendent Steve Klotz said the building that will function as an auxiliary gymnasium and emergency shelter for the community might not take a full year to complete. The design is simple. “It’s kind of like Legos,” Klotz said.