City hires Mozingo center architect
The Maryville City Council has entered into a contract with SFS Architecture of Kansas City for the design of a proposed new welcome center/administration building at Mozingo Lake Recreation Park.
A central component of the park’s master plan, completed last fall, the center is to be located along the main entry road near an existing check-in stand and will embrace an information desk, rental headquarters, gift shop, convenience store, storage space and offices.
Assistant City Manager Ryan Heiland said the facility will serve park patrons as “a go-to place for check-in, information, recommendations, rental equipment, reservations and concessions.”
As currently envisioned, the center will also offer food and beverage items for sale, along with gifts, use permits and bait; a game room; educational displays; and restrooms.
The building’s basement will provide storage and double as a park storm shelter.
Staff working out of welcome center offices are to include the park operations manager, maintenance manager, recreation coordinator, MOERA representative, receptionist and several interns. There will also be a conference room designed to accommodate up to 12 people.
SFS was one of ten firms that submitted proposals for the design contract, which carries a not-to-exceed price tag of $30,000, or around 10 percent of the estimated construction cost of between $250,000 and $400,000.
With regard to a second Mozingo project, the council awarded another contract this week for $104,444 to White Cloud Engineering & Construction of Maryville.
The agreement calls on White Cloud to execute “design-build” services related to expansion of existing wastewater treatment facilities at the city-owned park and reservoir.
White Cloud was the sole firm responding to the city’s request for proposals.
Heiland said the existing treatment facility at the park consists of a septic tank, recirculating sand filter and disinfection system rated to handle 8,000 gallons of effluent daily.
Enlarging the current system to perform in accordance with increasingly stringent environmental standards would be cost prohibitive, Heiland said, so White Cloud will replace it with a “zero discharge” system to be located east of the existing plant.
The system will disperse effluent over about an acre of ground and increase the park’s sewage treatment capacity to 10,000 gallons a day.
According to Heiland, zero discharge systems are preferred by the Missouri Department of Natural Resources for wastewater treatment conducted near reservoirs because they eliminate the direct release of ammonia and other pollutants.
Treated water from the current system is currently released into Mozingo Creek.
The 2014-’15 city budget earmarks $100,000 from the Mozingo Recreation Fund for the treatment system overhaul. Heiland said the additional $4,444 will come from the fund’s reserves.