City approves contractor for water treatment plant

FORUM FILE PHOTO
The city is planning to build a new water treatment facility to replace the existing plant that was built in 1958 with a new facility located at Mozingo Lake.

MARYVILLE, Mo. — The Maryville City Council on Monday selected a contractor to build and assist in the design of the new water treatment plant.

During Monday’s regular meeting, the council approved a bid from Crossland Heavy Contractors for construction manager at-risk services for the project. A construction manager at-risk model brings in the construction contractor during the design phase and locks in the price once design is complete, rather than bidding out a full design to construction contractors. When allowed by law, the city uses this model often to get better cost certainty.

“This project has had a number of milestones — right? — ever since we started down this path, and this may be one of the biggest, I think: to take this next step and enter into a contract with our contractor,” said council member Tye Parsons. “… Many of us in the room who have been here from the beginning of this process are just thrilled. Not only that the voters of our community passed the issue to move the water treatment plant forward, but just that we’re able to take this next, very large step and finally solve this thing once and for all.”

HDR, the longtime consulting firm that has been working with the city on a broad spectrum of water issues since 2020, led the search process for the right firm.

“We’re super stoked about this project,” said Joe Barnes, senior project manager at Crossland Heavy. “… We’re gonna work through the challenges and deliver you guys a great water treatment plant.”

Jessica Adams-Weber, a vice president and regional business development director at HDR, said that four high-quality contractors put in bids. But it was Crossland Heavy’s emphasis on the community that won out, she said, particularly the company’s interest in extending a successful internship program it has partnered with other colleges and universities on to Northwest Missouri State University.

“Like Jess said, we’re super excited about involving people in your community to be a part of our construction team — whether it be laborers, skilled craftspeople, subcontractors,” Barnes said.

Adams-Weber said the project is on target for substantial completion by November 2027. This month, the Missouri Department of Natural Resources approved Maryville’s application for a low-interest loan through the department’s Clean Water State Revolving Fund. Maryville voters approved a bond issue centered around the loan in a February special election.

Next, the city and HDR will work with Crossland Heavy on completing the design for the new ozone biofiltration plant, which would be the first of its kind in Missouri. Adams-Weber said the design is currently about 15 percent complete. The goal is to have the total maximum cost of the project locked in and guaranteed by October so that the city can secure a second loan for construction in November through Missouri DNR. Adams-Weber said the state agency has been in weekly contact with HDR about the project and understands “how critical this is for you guys as a community.”

Other City Council notes

  • Interim City Manager Ryan Heiland said that contractors working on Phase II of the South Main Corridor Improvement Project will be closing the road during the night intermittently over the next two weeks as crews install new storm sewer infrastructure. Check the city’s Facebook page for updates on times.
  • Heiland said the storm sewer project running from Judah Park to First Street is complete.
  • The council approved a $15,720 agreement with Dan Walter Concrete for the construction of a concrete pad for golf carts on the north side of the Mozingo Event Center. It will replace the existing gravel pad. Mozingo Lake Recreation Park Director Jordyn Greenhaw said that the original plan when the Event Center was constructed was for a concrete pad, but it was cut to save costs.
  • Council members also approved a $54,350 agreement with Dan Walter Concrete to build an 8-foot-wide, 665-foot-long concrete path from the new Mozingo Visitors Center to the existing ADA-compliant trails at Mozingo. Greenhaw said the concrete path is especially important to ensure safe and easy access to the Visitors Center since it will also serve as an emergency shelter. The cost will be split 50-50 between the city and a Community Betterment grant from the Missouri Department of Economic Development.
  • The city is still accepting responses until May 7 to community surveys on employment and child care as part of studies on the two topics. The surveys are available through the city’s website.

CORRECTION: The original version of this story incorrectly stated the expected in-service date of the new water treatment plant. Jessica Adams-Weber said the plant is on track for substantial completion by November 2027. The Forum aplogizes for the error.