South Main Phase II could begin late July, early August

CITY OF MARYVILLE
A rendering from Maguire Iron showing a possible version of the Spoofhound theme that could be painted on the Edwards Street water tower.
MARYVILLE, Mo. — Work on Phase II of the South Main Corridor Improvement Project could begin as soon as late next month, beginning the 18-month construction project that aims to complete the transformative overhaul of Maryville’s busiest roadway more than a decade after the first plans started to take shape.
During Monday’s regular meeting of the Maryville City Council, the council approved a contract with Genesis Environmental Solutions to build Phase II, which will run from the intersection of South Main with Missouri Highway V south to the U.S. Highway 71 intersection.
All told, the city estimates that Phase II will cost a little more than $8 million. That does not include moving overhead utility lines underground like in Phase I, which would cost an additional approximately $1.4 million should the city secure enough funding as the project moves along to add that component back in. Phase I’s total price tag came in at a little more than $13 million, according to city documents.
Phase II will bring the same types of improvements as Phase I did, including traffic and pedestrian safety additions, drainage improvements and aesthetic enhancements like lighting. Additionally, Phase II includes a raised median between Larry Lane and Horsepower Drive with landscaping in between.
City Manager Greg McDanel said during Monday’s meeting that work on the project could begin as soon as late July or early August, starting the 18-month clock on the construction — which he said was a conservative estimate.
Heading into the home stretch of Phase I’s construction last year, city officials had hoped to move quickly into Phase II, perhaps even overlapping the projects. But progress on Phase II was slowed when the city received only one bid for construction in August 2023 that was more than $10 million — significantly higher than the engineer’s estimate.
The city went back to the drawing board and pared down the project’s costs as much as possible, first by securing a Missouri Department of Transportation grant for $500,000 that will pay for the sidewalks included in Phase II, and then by breaking out the $1.4 million to move overhead utility lines underground.
When the city opened the bidding again this year, Genesis Environmental Solutions had the low bid at a much more manageable figure.
In addition to the $500,000 MoDOT grant, the city also received a $5.925 million federal Rebuilding American Infrastructure with Sustainability and Equity grant in 2022 that will cover the bulk of the funding needed. The city is also prepared to use $1.7 million in bonds for the project.
Other City Council notes
- The council approved a $61,700 agreement for engineering services with Snyder & Associates for the downtown pavilion project, which will erect a 40-by-80-foot covered pavilion downtown at a vacant lot at 106 E. Fifth St. The city was awarded half of the project’s estimated total cost through a Missouri Department of Economic Development grant in April of last year for $366,540. The other half of the funding will be matched locally through a combination of financing, fundraising and in-kind labor, city officials have said. McDanel said the goal is for construction to begin on the project by the end of this year.
- McDanel said that Maguire Iron has begun maintenance work on the Edwards Street water tower, which includes painting the exterior of the tower to show off Spoofhound pride. In April, McDanel said that since the city’s three water towers would need exterior painting anyway as part of scheduled maintenance over the next 10 years, Maguire could paint the towers with different basic designs and colors at no additional cost. The Edwards Street tower will be the “Spoofhound tower,” and include the Maryville school district logo on one side and Spoofhound lettering on the other, McDanel said. Down the line, the north water tower would be the “Bearcat tower” and the south tower would be the “city tower,” but those water towers likely won’t be due for maintenance for at least a few years still. The work on the Edwards Street tower will take six to eight weeks, McDanel said.
- Council members approved a $64,390 agreement with Estate Management Services of Missouri for algicide and application of the algicide to Mozingo Lake, which is done periodically to keep algae levels low. Algae on the lake has been linked to compounds that create taste and odor issues in the drinking water, like geosmin. The expenditure approved Monday had already been made in December but had not yet been approved by the council.
- The council also approved a $150,610 agreement with Nutrien Ag Solutions to purchase algicide to use this year. City staff have now been licensed to apply the algicide themselves, and so unlike the above ordinance, this agreement is only for the chemicals, not for applying the algicide.
- Council members approved a $12,975 agreement with Moffet Nurseries and a $16,600 agreement with Superior Fence to perform landscaping and fencing work at the Thomson Splash ‘N’ Play. Both agreements had been previously approved by the Maryville Parks and Recreation board. The improvements will be paid for through a grant from the Gladys M. Rickard Charitable Trust.
- The council reappointed Brian Schmitz and Bill Ingels to the Board of Code Appeals to three-year terms expiring July 1, 2027.
- Council members approved a request to close West Third Street between Ray and Grand streets from noon to 11 p.m. on July 4 for a neighborhood block party.
- The council approved a request by the Maryville Downtown Improvement Organization to close streets around the Fall into Fun event planned for Sept. 29. The event will celebrate the last Downtown Maryville Market and fall harvest, featuring market vendors, games, activities, food, drinks, music and a giant-pumpkin-growing contest.