Dedication scheduled for Hwy. 71 traffic ramp

TONY BROWN/DAILY FORUM
Except for striping and a few other chores, a traffic ramp linking the newly paved portion of 285th Street at the Kawasaki Motors plant in Maryville with southbound Highway 71 is essentially complete. A ribbon-cutting ceremony for the concrete roadway, which was funded by Kawasaki, is scheduled for 10 a.m. Tuesday, Aug. 29.

After more than a year and a half of construction, a new $2 million traffic ramp linking 285th Street south of the Kawasaki Motors plant to southbound Highway 71 is nearly finished.

Nodaway County Economic Development, which, along with the City of Maryville, played a key role in coordinating the Kawasaki-funded project with the Missouri Department of Transportation, has announced a ribbon-cutting ceremony for the new ramp scheduled for 10 a.m. Tuesday, Aug. 29, at the southeast corner of the Kawasaki campus.

The ramp, which is essentially complete except for striping and other final chores, begins with a “T” intersection on 285th Street just south of the factory.

Formerly a gravel road curving around the plant, the westbound portion of the “T” has been paved with concrete and links to a private drive leading to the Kawasaki loading docks.

From Kawasaki’s point of view, the improvements give 18-wheelers and other freight vehicles a way to access the plant’s shipping and receiving area without having to drive through the factory’s main parking lot and employee entranceway.

In addition, once the ramp opens, southbound traffic leaving the factory will no longer have to exit from the Kawasaki parking lot onto South Main near the stoplight intersection at the Highway 71 bypass.

Kawasaki’s Maryville facility employs more than 800 people, and the new ramp should reduce traffic congestion at and near the bypass intersection during shift changes.

Formerly owned by Polk Township, the newly improved part of 285th Street was transferred late last year to the city, which will now be responsible for snow removal and maintenance.

At the same time, the city also accepted ownership of South Main between Route V and the Highway 71 bypass interchange — the last section of South Main that had remained under MoDOT control.

City Manager Greg McDanel said at the time the transfers will simplify proposed long-range improvements intended to transform the South Main retail strip into a tree-lined, pedestrian-friendly boulevard.

West of Kawasaki, 285th Street reverts to gravel and remains under the control of Polk Township, but city officials have speculated the passage could someday become a paved city street providing an east-west link between Main Street and Icon Road.

Maryville-based White Cloud Engineering & Construction serves as general contractor for the ramp project, which has also embraced relocation of gas, water, telephone and fiber optic lines.