Local companies fill county’s rebar order

TONY BROWN/DAILY FORUM
Steel mats woven from rebar reinforcing rods lay stacked outside Nodaway County’s maintenance garage at the corner of South Depot and East Halsey streets. Last week the County Commission accepted a low bid from Maryville Lumber to provide additional rebar, which will be used to reinforce the concrete decks of seven rural bridges scheduled for construction later this year.

The Nodaway County Commission continued preparing for this year’s bridge construction season last week during its regular Friday session.

Presiding Commissioner Bill Walker opened five bids from companies seeking to provide the county with steel “rebar” rods, which are used to reinforce concrete poured to form bridge decks.

The low bid of $12,825 for approximately 45,000 pounds of rebar was turned in by Maryville Lumber, which sells rebar produced locally by Nucor-LMP Steel.

Other bidders included Viebrock Construction of Sedalia; The Railroad Yard, Stillwater, Oklahoma; Midwest Service & Sales Co., Schuyler, Nebraska; and Oden Enterprises, Wahoo, Nebraska.

All five bids were fairly close, ranging within $3,000 to $4,000 of each other.

The material is to be delivered as two half-semitrailer loads consisting of rebar in 13- and 20-foot lengths. Once at the county maintenance barn in Maryville, the Nodaway bridge crew will wire the steel rods together into 13-by-20-foot mats, which are laid longwise two abreast to form the reinforcing grid used to strengthen concrete decking.

The commission has proposed an ambitious bridge construction program this year that includes seven projects scattered across five of Nodaway’s 15 townships.

South District Commissioner Robert Stiens, who acts as the commission’s lead official for transportation matters, said the 2017 bridge budget comes to a little more than $1 million, money that is derived from locally collected sales taxes on gasoline and diesel fuel.

Of the seven bridges on the list for rebuilding over the spring and summer, only three are on gravel roads. These include spans near the intersection of 240th Street and Mahogany Road just east of Mozingo Lake.

Road and Bridge Supervisor Ed Walker said the trio of bridges will likely be the first projects undertaken when construction season begins, since the structures will be easier to reach with heavy equipment during what is normally wetter weather in the spring.

The remaining four spans on the county’s to-do list are all on dirt roads, and three of them are currently closed to traffic.

Closed spans to be replaced include a 100-foot-long bridge in Hughes Township near the intersection of 350th Street and Fairway Road northeast of Graham, a 90-foot bridge in Atchison Township near 120th and Hallmark, and a 100-foot bridge in Union Township near 180th Street and state Route FF.