Skip to content

Airport runway rebuild set for end of May

TONY BROWN/DAILY FORUM
Most of the runway and northernmost taxiway at Northwest Missouri Regional Airport will be reconstructed this summer using $3 million in funding provided by the Federal Aviation Administration’s Airport Improvement Program. The project has a total estimated cost of nearly $3.4 million and includes a $338,000 local match to be financed using a Missouri Department of Transportation Statewide Transportation Assistance Revolving Fund loan. Depending on the weather, the airport will close for about four months after construction begins sometime around the end of May.

City officials are gearing up for major renovations at Northwest Missouri Regional Airport this summer that will include replacement of most of the landing field’s 4,600-foot-long concrete runway as well as the northernmost of two connecting taxiways.

The nearly $3.4 million project will also embrace installation of new runway and taxiway lights, a new wind cone, and associated electrical wiring and fixtures.

Assistant City Manager Ryan Heiland, who serves as lead administrator for airport operations and facilities, will participate April 19 in a preconstruction meeting with general contractor Ideker Construction of St. Joseph and representatives from project designer JViation Inc.

The session is expected to produce a detailed timeline for construction, which is supposed to begin around the end of May and continue for about four months, during which the facility will be closed to aircraft.

Pavement ruptures during hot weather have become an increasingly common problem at the airport, which has closed several times in recent years for emergency repairs.

This summer’s rebuild does not include the southernmost 600 feet of the runway, which was added as an extension in 2008 along with a second taxiway.

The remainder of the 75-foot-wide airstrip, all of which is slated for replacement, was built in the mid-1990s.

Total project cost, based on a $3 million low bid from Ideker accepted by the City Council last August, is just under $3.4 million. More than 90 percent of the funding will come from a Federal Aviation Administration Airport Improvement Program grant.

The city is responsible for a $338,800 local match financed using a Missouri Department of Transportation Statewide Transportation Assistance Revolving Fund loan — a program known as STAR.

Authorized by the Missouri General Assembly, STAR was created specifically to provide low-interest loans to local governments for non-highway projects such as railroads, waterways, and air travel infrastructure.

Maryville’s loan is to be paid back over 10 years at an interest rate of just under 2 percent.

Aside from the need for increasingly frequent repairs to cracked and buckled pavement, Heiland has said that pilots of small jets sometimes radio ahead before landing at Maryville to request that the runway be cleaned, fearing that small chunks of loose pavement will damage their aircraft.

Other problems the upcoming project is to fix include approach lights that stand at different heights, thus creating a potential hazard during night landings. In addition, the lights, which are supposed to be activated via air-to-ground radio signals, sometimes fail to switch on at all.

Long known as Maryville Memorial Airport, the landing field was built after World War II and renamed in 2003.

Recent improvements include a terminal building completed in 2007 and the installation of a two-tank fuel island in 2009 that dispenses both aviation gasoline and jet fuel.

TONY BROWN/DAILY FORUM
Patched pavement and aging concrete are becoming serious concerns at the Northwest Missouri Regional Airport, located west of Maryville just north of Highway 46. Most of the landing field’s runway, plus a connecting taxiway, both built 20 years ago, are to be replaced this summer using a $3 million grant through the Federal Aviation Administration.

Leave a Comment