Earthwork has begun at the construction site of the Mullin Creek Substation south of Maryville. The station is part of the Midwest Transmission Project, a high-voltage power line initiative undertaken jointly by Kansas City Power & Light and the Omaha (Nebraska) Public Power District. When completed the 345-kilovolt line will stretch 180 miles from KCP&L’s existing Sibley (Missouri) Substation to OPPD’s Substation No. 3458 south of Nebraska City, Nebraska.

More power. That’s the answer to the question motorists are asking about all the heavy equipment and earth-moving activity just to the west of Highway 71 at 340th Street about seven miles south of Maryville.

The site will soon be the location of the new Mullin Creek Substation, which is part of the Midwest Transmission Project, a high-voltage power line initiative undertaken jointly by Kansas City Power & Light and the Omaha (Neb.) Public Power District.

When completed, the 345-kilovolt transmission line will stretch 180 miles from KCP&L’s existing Sibley (Missouri) Substation, through the Mullin Creek facility, and on to OPPD’s Substation No. 3458 south of Nebraska City, Nebraska.

Kansas City Power & Light spokesperson Courtney Highly said the Mullin Creek substation marks the dividing connection between the KCPL and OPPD portions of the project.

In addition to Nodaway, the line also travels through portions of Ray, Caldwell, Clinton, DeKalb, Andrew and Holt counties in Missouri and Richardson, Nemaha and Otoe counties in Nebraska.

A route map for the project can be viewed at www.midwesttransmissionproject.com.

The Missouri portion of the line — at roughly 135 linear miles by far the biggest part of the project — is being constructed by Transource Energy, an entity formed by Great Plains Energy, KCP&L’s holding company, and power giant American Electric Power, which owns a controlling interest in Transource.

According to the Midwest Transmission Project website, the Mullin Creek Substation’s location was selected due to its proximity to existing lines, the size and geography of the available property, and the potential for screening and landscaping “to minimize visual and environmental impact.”

As it began laying the groundwork for construction in 2012, KCP&L officials and others associated with the project conducted a series of public meetings with landowners and county officials in an effort to lessen the impact on homes, farms, cemeteries and environmentally sensitive areas.

More than 2,000 residents attended 20 public open houses, including two in Maryville, over a 10-month period, KCP&L officials estimated.

Landowners over whose property the line passes are receiving one-time cash payments in exchange for granting easements ranging in width from 100 to 160 feet.

Partnership officials estimate construction cost at $400 million, and say the effort will create between 50 and 70 construction jobs. The investment is to be recouped from electricity customers throughout the Southwest Power Pool, which embraces utilities in parts of nine states: Arkansas, Kansas, Louisiana, Mississippi, Missouri, Nebraska, New Mexico, Oklahoma and Texas.

Construction began this summer and is to continue over the next two years.

When completed, the Missouri portion of the line will consist of large H-pole structures standing up to 100-feet high and supporting 1,000-foot spans of high-voltage cable.