An intergovernmental agreement between the city of Maryville and Polk Township means that West South Avenue will get a fresh coat of asphalt this summer between Main Street and Icon Road. The heavily traveled route provides eastbound access to the South Main retail corridor and Maryville High School in addition to westbound access to the newly completed Oak Pointe assisted living complex located north of the Icon/South Avenue intersection.

Slowly but surely the bumpy road into Maryville is getting smoother.

A decade ago, Polk Township got voter approval for a temporary property tax levy called “Pave Me for Pennies,” proceeds from which were used to pave Icon Road south into the city limits from Highway 71.

Then, a couple of years ago, the city was able to negotiate a deal with the Missouri Department of Transportation under which the state redesignated East First Street as Highway 46 in exchange for the city accepting ownership of Third Street, the highway’s former route.

The agreement included the resurfacing in 2014 of East First, mostly at MoDOT’s expense, improving a second major access point into the city.

Also last year, MoDOT improved South Main Street north into town from the south end of the Highway 71 bypass.

A third ingress route, Jet Road/North Depot south into Maryville from the north end of the bypass, has also been improved in recent years with overlays at both ends of what was once a badly dilapidated street.

With West First street in good repair from the west city limits to Main Street and Highway 71 on MoDOT’s priority maintenance list, only two real trouble spots remain for motorists on their way into town: West South Avenue between Icon Road and South Main and North Main from twelfth Street to the north end of the bypass.

And one of those bumpy thoroughfares — West South Avenue — is on the to-do list this summer for both the city of Maryville and Polk Township, with each government entity planning to resurface the section of road under its control.

The city’s share of West South Avenue ends just west of Parkade Road, where the thoroughfare curves south and becomes 270th Street. Polk Township takes over where the street straightens to the west again and continues to Icon.

Earlier this spring, the Maryville City Council placed West South Avenue on its list of summer repaving projects, nearly $500,000 worth of asphalt overlay work to be accomplished by Keller Construction of St. Joseph that also includes Katy Drive, Prather Avenue, West Ninth Street, West Eighth Street, East Fourth Street between Vine and Davis, North Ray between Third and Fourth, North Munn between College and First, South Munn between First and Edwards, West Crestview Drive, and West Fourth Street (College Avenue) between Dunn and Grand.

Keller will also lay down new pavement on several roads at Mozingo Lake Recreation Park.

Polk Trustee Blake Degase said the township has set aside $38,000 for its share of West South Avenue, called 270th Street west of the city limits. The township is also working to widen the ditches on both sides of the road in an attempt to improve drainage and keep as much water as possible off the new asphalt.

Degase said the repaving of West South Avenue/270th is scheduled for sometime in June, and that negotiations are under way with City Hall about the possibility of Maryville assuming maintenance responsibilities for the entire street.

The proposal for city ownership of 270th to Icon, Degase said, has to do with the need for snow removal and road maintenance along a convenient route into town for residents and employees at the Oak Pointe assisted living center, located on the city’s portion of Icon, which is designated Country Club Drive.

As for Main Street north to the bypass, motorists won’t see any improvements this year. With an estimated resurfacing cost of more than $200,000, the heavily traveled two-mile stretch of highway is out of the city’s fiscal reach under the current budget.

However, City Manager Greg McDanel has said asphalting Main from Twelfth Street north is a priority, and that municipal staff plans to apply for a state Community Development Block Grant that could provide up to 80 percent of the funding for the project.

Grant or no grant, McDanel said he believes the city will have to move forward with repaving North Main in the fairly near future because the dilapidated corridor serves as an important northern gateway into town and is heavily used by visitors, commuters and college students.