Tenaska, Associated Electric sign wind power deal

SUBMITTED IMAGE
The dashed-line rectangle on this map shows the area across which the Tenaska company plans to build Nodaway County’s second wind farm, which has been named the Tenaska Clear Creek Energy Center. On Monday, the independent power producer hosted an event celebrating the signing of a long-term power purchase agreement with Associated Electric Cooperative Inc., an energy wholesaler headquartered in Springfield.
MARYVILLE, Mo. — Omaha, Nebraska-based independent power producer Tenaska on Monday hosted an event at Northwest Missouri State University celebrating the signing of a long-term power purchase agreement with Associated Electric Cooperative Inc., an energy wholesaler headquartered in Springfield, Missouri.
Terms of the deal specify that Tenaska will sell power to Associated Electric produced by a 236-megawatt wind farm, known as the Tenaska Clear Creek Energy Center, to be constructed in northern Nodaway County.
The 25-year purchase agreement is a key step forward in continued development of Clear Creek, which is set for construction in 2019 and scheduled to go operational in 2020.
Associated Electric Cooperative is owned by and provides wholesale power to six regional and 51 local electric cooperative systems in Missouri, southeast Iowa and northeast Oklahoma. Those co-ops serve a total of nearly 1 million member-customers through a mix of coal- and natural gas-powered plants, wind farms and hydroelectric installations.
Co-ops doing business with Associated include United Electric Cooperative, which serves rural customers throughout Andrew, Gentry and Worth counties in addition to portions of Nodaway, Holt, Buchanan, DeKalb and Clinton counties. UEC also provides power to portions of Page, Taylor and Ringgold counties in Iowa.
“We are excited to be starting a new relationship with Associated, a relationship that will bring more renewable (power) generation and significant economic benefits to the region,” said Greg Kelly, president and managing director of Tenaska’s Strategic Development & Acquisitions Group.
“We look forward to completing development and construction of Tenaska Clear Creek and putting this project into operation.”
Tenaska’s power holdings currently include approximately 10,000 megawatts of natural gas-fueled and renewable power projects.
“This agreement secures long-term, fixed and competitively priced renewable energy for our members, serving as a buffer against projected increases in fuel prices,” said David J. Tudor, Associated’s chief executive officer and general manager.
“With our experience managing significant amounts of wind power on our system, Clear Creek is a good fit for our power supply portfolio.”
The Clear Creek project will use Associated transmission connections and comprise 100 to 120 wind turbines, each producing between 2 to 3 megawatts of electricity.
Turbines are to be supplied by Vestas Wind Systems A/S, a Danish company that is one of the world’s largest wind technology manufacturers.
Tenaska officials estimate Clear Creek’s construction cost at between $200 million and $300 million, and say the project will create more than 200 jobs during the peak construction period. An additional 15 full-time local jobs are anticipated once the wind farm starts generating power.
The company also predicts an anticipated increase in tax revenues of around $1.2 million a year that will benefit a number of Nodaway County government and public entities, including the Maryville, North Nodaway and West Nodaway school districts.
Another $1.2 million is to be paid out annually to landowners who allow turbines to be erected on their property.
“I wanted to level-set everyone’s understanding of the importance of the power purchase agreement,” Kelly said during the Northwest event. “It’s the contract that provides the revenue stream once the project is operational that’s needed to finance the project and advance the construction.
“In other words, one of the — if not the most important — components in raising the substantial capital required to move ahead with the project.”
UEC Chief Executive Officer Jim Bagley said he expects Clear Creek to have a significant impact on the Maryville area.
“As long as the property rights our members are respected,” Bagley said, “the economic impact of this project will benefit Nodaway County through the property taxes that will be paid and the employment this project will create. What is good for Nodaway County is good for United Electric and its member-owners.”
He added that the Clear Creek agreement should serve as “a good hedge for our partner, Associated Electric, to keep wholesale electric prices down” for the next two and a half decades.
“Being able to lock this price in is one of the few things we control over the next 25 years for our power future,” Bagley said. “Associated does a great job of long-term planning, and this is just another part of it.”

PHIL COBB/THE FORUM
Monte D. Ten Kley, Director for Tenaska’s Systems Strategic Development and Acquisitions Group and Project Manager for Tenaska’s Clear Creek Energy Center, speaks Monday evening.

Greg Kelly Tenaska President and Managing Director of Strategic Development and Acquisitions

Joel Wilkinson Associated Electric, Senior Vice President/Chief Member Relations Officer

Barry Hart Executive Vice President and CEO of the Association of Missouri Electric Cooperatives

Jim Bagley Chief Executive Officer for United Electric Cooperative