City Manager Greg McDanel said this week that Kawasaki Motors Manufacturing Corp. has met job creation and retention goals imposed as part of a 2015 tax incentive deal tied to a 100,800-square-foot plant expansion.
In his twice-monthly report to the City Council, McDanel said a performance agreement associated with the $25.5 million expansion required Kawasaki to maintain an average of 30 new jobs above a minimum of 775 employees on the payroll as of Dec. 31, 2017.
In addition, the agreement specified that those jobs pay a wage exceeding the Nodaway County average.
As of last year’s test date, McDanel told the council, the local plant employed 837 people, a number that exceeds the minimum requirement by 32 employees.
He added that new jobs created following the expansion pay an average of $19.81 per hour, which is $4.51 more than the wage rate required under the Missouri Quality Jobs Act.
The minimum number of local Kawasaki Motors jobs required under the abatement deal totals 805 through Dec. 1, 2025.
Approved by the council in March 2015, the abatement package consists of $25.5 million in industrial revenue bonds — also known as Chapter 100 bonds — issued by the city, purchased by Kawasaki and payable solely from revenues derived from the expansion.
The bond issue was made in conjunction with a 100 percent tax abatement on real property and a 50 percent tax abatement on new personal property over 10 years.
Under the agreement, Kawasaki is required to make a payment-in-lieu-of-taxes equal to the amount of real property taxes to ensure that public entities, such as the Maryville R-II School District, continue to receive revenue.
McDanel noted that while taxes that would have been collected on the expansion were partially abated, the project has nevertheless generated new revenue for all affected taxing jurisdictions.
Now complete, the Kawasaki expansion embraced a $7 million investment that created more than 100,000 square feet of production floor space. The remaining $18.5 million was used to purchase new equipment.
“Chapter 100 bonds allow for a certain percentage of property tax abatement,” McDanel said. “However, the use of the incentive itself encourages new investment and new revenue for the taxing entities.
“The bond process also includes performance agreements to ensure the industry meets project goals.
“We are pleased to report that Kawasaki has exceeded minimum job and pay numbers and continues to be a great corporate citizen of this community.”