Jefferson gymnasium still waiting on floors

TOM PINNEY/DAILY FORUM
Pictured is the exterior of the new gymnasium at Jefferson C-123 School. While the new driveway has been poured and the foyer finished, the interior of the gym still awaits completion as the floors have been delayed several times.
In April 2016, voters in the Jefferson C-123 School District finally approved a measure that would provide funding for a new gymnasium at the school. By the fall, the district had secured a design, chosen St. Joseph-based E.L. Crawford as the contractor, and had planned for the new facility to be completed by the end of May, 2017.
Unfortunately, that’s not how things ended up going. After an unusually wet spring and stormy summer, the completion date was pushed back several times. In June, superintendent Tim Jermain remained hopeful that the gym would be ready for the first day of school.
The main holdup for the gymnasium’s completion has been the wood floors. The subcontractor in charge of the floors, whose name is not included because Jermain said all the subcontracting work has been handled by E.L. Crawford, initially gave the district an arrival date of July 5, but that date changed several times.
The new date the district has been given is Tuesday, Aug. 29. But Jermain isn’t terribly confident in that date.
“It’s hard to be confident when there have been so many setbacks,” Jermain said. “We were originally told there would be a two-week delay, but this is the fourth or fifth date we’ve been given from our flooring subcontractor.
“They’re more hopeful that next Tuesday is the day, and it sounds more promising now than it did before, but until it shows up I’m hesitant and wouldn’t want to make any guarantees. That’s the big delay that’s holding everything up right now.”
Jermain noted that there are several things that still need to be done in the gym, but most of them hinge on the floors being installed and complete. One example is that the bleachers, which can’t be set up until the floor is not only laid, but settled in the foundation, have been at the school since early July.
This has understandably caused some frustration on Jermain’s part, on the district’s part, and on the part of E.L. Crawford.
“They’ve been sitting here with a project that’s just on the brink of being done,” Jermain said. “They’re just as frustrated as I am because they have other projects they can’t move on to until they’re done here.”
The original contract did not include any sort of incentive or punishment based on the completion date, as the date the district was given was merely a projection.
As far as what has been holding up the floors, Jermain said it goes all the way back to the lumber mills.
“What we’ve been told is that there was an early fall up north which prevented trees from getting to the lumber mills to get cut,” Jermain said. “The mills haven’t had the supplies they’ve had in the past, so the company gets delayed in making the floors and sending them out.
“This isn’t really a delay on the subcontractor’s part, but it’s due to the lack of materials. It was an unavoidable circumstance.”
Because of that, Jermain said he sympathized with the situation, no matter how frustrating it was.
“Our experience, other than this, has been extremely positive,” Jermain said. “E.L. Crawford has been great to work with, and the foreman has had our best interests in mind the whole time.
“Our architect has said that he’s worked with the flooring subcontractor a number of times in the past, and that this is the first time such an issue has happened. Extenuating circumstances happen, and this was one of those events that was outside of their control that ends up being just bad for everyone.”
If the floors do arrive on time on Tuesday, Jermain said the gym would be complete near the end of September. Until that point, and in case of another setback, the district has contingency plans.
“We have an alumni event through the Foundation scheduled for the end of October and basketball starts for junior high in mid-October,” Jermain said. “We can always use our old gym for basketball and we’re talking about rescheduling the alumni event.
“We also are hosting the junior high basketball tournament, and South Nodaway has said they will host some games if they need to. The big thing that we’re waiting on the gym for is to use it for elementary recess and different activities. While the weather is nice, we can go outside, but as we get closer to the winter, we’ll need the gym more.”