Sewage plant, streets taken up by council

TONY BROWN/DAILY FORUM
Construction work is moving into its final phases at the new Maryville wastewater treatment plant. A series of weather-related delays has pushed facility completion back to May 10, which Public Works Director C.E. Goodall said still leaves sufficient time to bring the plant online prior to a state-imposed deadline of July 1.
The Maryville City Council this week approved relatively minor changes in its agreement with David E. Ross Construction Co., which is entering the final stages of work on the city’s new $13.7 million mechanical wastewater treatment plant.
The latest round of contractor-requested changes is the second contract alteration since the project began and will add $89,000 to the originally agreed on construction cost.
The original bid of $11,438,800 decreased $58,000 following an earlier change order late last summer, which included both contractor efficiency savings and an additional $180,000 required for a lift station upgrade.
The upgrade related to difficulties in “de-watering” the construction site that meant several large concrete structures designed to hold and treat sewage had to be raised several feet higher than called for in the original design.
Installing bigger pumps at the lift station and reconfiguring the depths of the structures, including two massive clarifier tanks and an aeration basin, also added $30,000 to the project’s engineering bill.
To offset those costs, city officials opted to replace a planned concrete parking at the sewer plant with gravel, a move that combined with the earlier savings kept the project under budget.
The newest round of changes raises the total Ross contract to $11,469,664, which amounts to a .27 percent increase over the original agreement.
By ordinance, administrative approval is allowed of sewer plant construction change orders calling for increased costs of to 2 percent, or around $229,000. This week’s alteration falls easily within that limitation.
Contract revisions approved Monday by the council include:
• A modified scope of work to remove a permanent access road leading to private property that is to be returned to farmable condition at an increased cost of $14,129.
• Upgrading electrical components at the city’s East Lift Station ($62,943).
• Structural changes to a disinfection structure ($1,610).
• A modified scope of work related to installation of a supervisory control and data acquisition computer system. ($2,152).
• Addition of paved parking slots at the Operations and Headworks Building ($12,600).
• The addition of 30 days’ working time to the contract due to weather delays between March 2014 and January of this year.
Of the six changes, the most crucial is the last, since the city is under a mandate from the state Department of Natural Resources to have the new plant on line by July 1.
The delay pushes the facility’s substantial completion date back to May 10, which Public Works Director C.E. Goodall said still allows “ample time” to get the plant operational prior to the deadline. Failure to do so could result in punitive fines charged to the city for failure to meet state and federal environmental regulations.
In other business during its regular session on Monday, the council, as expected, approved a street overlay contract with Keller Construction Co. of St. Joseph for a not-to-exceed amount of $674,215.
The base bid submitted by Keller calls for the resurfacing of the following thoroughfares: Katy Drive, Prather Avenue, W. Ninth Street, W. Eighth Street, E. Fourth Street between Vine and Davis, N. Ray between Third and Fourth, N. Munn between College and First, S. Munn between First and Edwards, W. Crestview Drive, and O’Riley Road and Ridge Road at Mozingo Lake Recreation Park.
In addition, the bid was low enough to encompass several “alternate” projects, including West Fourth Street (College Avenue) between Dunn and Grand, South Avenue from South Main to the west city limits, and additional work at Mozingo Lake embracing roads serving the reserved recreational vehicle camping area, Songbird Road, the parking lot for rental cabins Nos. 6 and 7 and various localized pavement repairs.
The council budgeted $400,000 for asphalt overlays in this year’s budget and another $150,000 for street work at Mozingo.
City Manager Greg McDanel said the contract calls for $483,201 in General Fund spending and $167,070 in spending from the Mozingo Recreation Fund. In addition, Northwest Missouri State University is contributing $23,944 for paving the north-side parking lane along West Fourth.
The difference is to be made up using about $100,000 of $254,000 in savings accrued this year when the city switched health insurance providers.