Though its five members worked swiftly through a light agenda this week, the Maryville City Council has a lot on its plate these days, as evidenced by the twice-monthly report delivered by City Manager Greg McDanel.
Major projects currently under way include streetscape construction on West Fourth, where crews this week have been installing vintage-style streetlamp posts along the newly poured sidewalk.
Also on the horizon, McDanel said, is this spring’s annual round of asphalt street overlays, budgeted in 2015 at around $400,000.
Later this month, city officials will open contractor base bids for the following roadway segments: Katy Drive; Prather Ave; W. Ninth; W. Eighth; E. Fourth from Vine to Davis; N. Ray from Third to Fourth; N. Munn from College to First; S. Munn from First to Edwards; W. Crestview; and O’Riley Road and Ridge Road at Mozingo Lake Recreation Park.
The overlay plan also includes several alternates — jobs to be undertaken if enough money is available — including Fourth Street from Dunn to Grand; E. Edwards (blocks 300 to 500); South Avenue from Main to the west city limits; S. Saunders from Torrance to South Ave; Carefree Drive from Galaxie to W. Serenity Loop; and the reserved RV camping area roads and Songbird Road at Mozingo.
An optional pre-proposal meeting for interested contractors will take place at 10 a.m. Thursday at City Hall. Formal bids are due no later than 10 a.m. on Thursday, Feb. 26, with the contract award scheduled for the Monday, March 9, council meeting.
The tentative schedule calls for completion of all overlay projects between April 1 July 31.
In addition to looking forward to spring, McDanel this week also glanced back to a pair of winter storms that struck the Maryville area during the first week of February.
Together, he said, the two storms dumped about a foot of snow on local thoroughfares and forced the city’s seven-member maintenance crew to spend long hours clearing streets behind the wheels of salt spreaders and bladed trucks.
McDanel said the team spread approximately 130 tons of treated salt in order to melt layers of ice that formed beneath packed snow at a cost of $14,575 for materials and $5,000 for labor, including overtime. The expenditure consumed roughly two-thirds of the city’s total snow-removal budget.
On other fronts this week, the council was asked to approve a pair of lot splits for a street extension and construction of two additional 16-unit apartment buildings at Southview Apartments on South Main Street.
The project has received approval from the Missouri Housing Development Commission and is on the agenda as a Planned Unit Development during today’s meeting of the Maryville Planning and Zoning Commission, which convenes at 5 p.m. at City Hall.
Other upcoming municipal projects outlined for the council this week include a 1,400-foot sewer main replacement on Prather Ave., where insufficient line elevation has resulted in numerous backups during heavy rains.
Work on the 8-inch main was to begin this week with installation of the first 400 feet of pipe and two new manholes by local contractor White Cloud Engineering, which is using the parking lot of Robertson-Crist Park as a staging area. The $129,000 project cost is included in this year’s budget.
Also on tap are a couple of projects at Mozingo Lake Recreation Park, where the city is planning to construct a new welcome center, which was identified as a top priority in a park master plan adopted by the council last year.
A number of architectural firms have responded to a request-for-qualifications with regard to designing the proposed facility, and McDanel said he expects to make a contract recommendation to the council later this month.
The second Mozingo initiative on the drawing board is a sewage treatment expansion that would increase capacity of the existing septic tank/sand filter/disinfectant system from 8,000 to 10,000 gallons of effluent per day.
The project is meant to prepare the park for future growth while ensuring compliance with Missouri Department of Natural Resources requirements.
Contractor bids for designing and building the expansion are due at City Hall at 10 a.m. Tuesday, March 5, with the council scheduled to award the contract on either March 9 or March 23.
Another construction project on a somewhat smaller scale is planned for the Maryville drinking water purification plant, according to McDanel and Public Works Director C.E. Goodall. In response to a state DNR recommendation, the city plans to construct a small block or concrete addition to the existing plant that will be used to store chlorine dioxide.
Though a key component in the water purification process, chlorine dioxide is toxic and corrosive to metal. Goodall said the chemical is currently stored in a building separate from the main plant that nevertheless includes vales and other mechanical fixtures.
A separate 8-by-10-foot room dedicated to chlorine dioxide storage, Goodall said, will both create a safer work environment for plant staff and reduce the likelihood of contamination and equipment damage.
Contractor bids for construction of the addition are due at City Hall by 1 p.m. Thursday, Feb. 19.

TONY BROWN/DAILY FORUM
Sections of 8-inch pipe lay stacked Tuesday in the parking lot of Robertson-Crist Park, which is being used as a staging area by White Cloud Engineering during construction of a new sewer main along Prather Avenue. The 1,400-foot main is designed to prevent the frequent backups that have plagued the neighborhood during heavy rains.