City reviews 2015 street overlay options

TONY BROWN/DAILY FORUM
TONY BROWN/DAILY FORUM The Maryville City Council has some big-money decisions to make this winter with regard to the annual campaign to apply fresh asphalt to decaying streets. One priority, according to City Manager Greg McDanel, is North Main between Twelfth Street and the north end of the Highway 71 bypass, shown above. While on the list of potential overlay projects that could be completed this year, it is more likely the city will seek a Community Development Block Grant for North Main, which would set back the job until summer 2016.
The Maryville City Council this week began considering its options for what has become an annual street overlay program, and one of those choices calls for the asphalt resurfacing of the decaying portion of North Main between Twelfth Street and the north end of the Highway 71 bypass.
Though rehabbing North Main tops the second of two base-bid lists submitted to the council for consideration Monday, it is more likely that the job, with an estimated cost of more than $200,000, will not be undertaken until spring 2016.
City Manager Greg McDanel said waiting another year will give municipal staff time to prepare and submit an application for a state Community Development Block Grant that could provide up to 80 percent of the funding.
Grant or no grant, McDanel said the city will have to move forward with repaving North Main within the next year or two, since the corridor is in rough shape and serves as an important northern gateway into town heavily used by visitors, commuters and students at Northwest Missouri State University.
“That’s the (street) I get calls about the most,” said Public Works Director C.E. Goodall. “We spend a lot of time out there patching, and the patches just don’t hold up.”
Vital though it is, repairing the 2-mile stretch of what is essentially a municipal highway will cost fully half the city’s entire $400,000 annual overlay appropriation. Meaning that, should the council decide to fix North Main this year, the list of remaining streets to be asphalted would be significantly shortened.
Base bid No. 1 submitted to the council leaves out North Main and calls for the resurfacing of the following thoroughfares: Katy Drive, Prather Ave., W. Ninth Street, W. Eighth Street, E. Fourth Street between Vine and Davis, N. Ray between Third and Fourth, N. Munn between College and First, S. Munn between First and Edwards, W. Crestview Drive, and Davis Street between First and Edwards.
Base bid No. 2, in addition to North Main would include: Katy Drive, Prather Ave., W. Ninth, E. Fourth between Vine and Davis, and W. Crestview Drive.
In addition to the streets listed above, the city is also expected to seek contractor offers on a number of “alternate” projects that would be funded should bids come in below estimates.
Alternate streets, each to be bid separately, include Fourth Street between Dunn and Grand, the 300-to-500 blocks of E. Edwards, South Avenue from Main to the west city limits, and S. Saunders from Torrance to South Avenue.
As with North Main, a couple of the alternates would take a chunk out of available overlay funds, especially South Avenue, which carries an estimated price tag of $128,000.
Once one of the two base bid packages is approved, McDanel said he expects the city to issue a request-for-proposal to qualified contractors sometime next month.
In addition to paving streets in town, the city is expected to spend an additional $150,000 on asphalt projects at Mozingo Lake Recreation Park, which has its own revenue stream generated through user fees and a half-cent sales tax.
The base bid options call for repaving either a portion of the park’s main artery, Ridge Road, or O’Riley Road, which leads toward lakeside rental cabins and recreational vehicle camping areas.
If there’s enough money, the city will also consider a couple of alternate projects, including asphalting the gravel road that leads to the reservable RV campground and the paving of Songbird Road, which provides access to three newly constructed cabins across a cove from the golf course.
Though the process of keeping smooth asphalt on city streets is both expensive and never-ending, Councilman Jeff Funston said the effort is a responsibility city officials can ill afford to shirk.
He noted that only a few years ago Maryville was spending $100,000 a year or less on asphalt projects and is now paying the price for that lack of fiscal commitment.
“You’ve got to get at least $500,000 into this each year,” Funston said. “Somehow you just have to find that money.”