Alleyway project set to start Oct. 6

CONFLUENCE/CITY OF MARYVILLE
A previous rendering shows a section of a downtown alleyway project at night. Construction on the pedestrian-focused corridor is slated to begin Oct. 6 and could be completed by June 2026.

MARYVILLE, Mo. — Work on the downtown pedestrian alleyway is slated to get underway on Oct. 6 with an eye toward completion in June of next year.

Maryville City Manager Ryan Heiland gave the update during Monday’s regular City Council meeting.

The project will reimagine the alley between Bank Midwest and The Pub heading west past Kris and Kates. The pedestrian-focused corridor will feature accessible pedestrian walkways, moveable bench seating, suspended lighting, vine trellis walls, turf berms and significant landscaping work. On the Main Street side of the alley will be a ready-made photo op, with “MARYVILLE” spelled out, but missing the “Y,” giving people the opportunity to take photos as the “Y.”

In July, the council approved a $1.4 million contract with MegaKC to construct the alleyway along with a separate $197,728 contract with the company to improve a north-south alleyway that runs from Fifth to Fourth streets between Main and Buchanan streets. The project will remove the existing gravel, add drainage features and add a six-inch rock base before paving over it with seven inches of concrete. That project will be on the same timeline, Heiland said.

East Thompson Street Trail

Also during Monday’s meeting, the council approved two changes to the construction plan for the East Thompson Street Trail.

The project will add a concrete trail of approximately 1,600 feet from South Davis Street to South Laura Street, connecting the existing trail network along South Davis Street to the Maryville Housing Authority and additional neighborhoods on the east side. The project was awarded a Transportation Alternatives Grant by the Missouri Department of Transportation in 2022, which will pay for 64 percent of the cost.

Monday, the council approved a $20,600 change to the plan because some elements of the original design did not meet Americans with Disabilities Act standards. Grant funds will take care of most of the cost; the city’s share will be $7,416.

Additionally, the council also approved a $5,700 addition to the project that will construct a 26-foot-long retaining wall near Davis Street to address backslope grading concerns and extend the retaining wall at the east end of the project near Laura Street to tie into a proposed set of stairs located near the Thomson and Laura streets intersection. The city’s share of that addition is $2,052.

Other City Council notes

  • The council approved a $26,759.67 agreement with Red Equipment to replace a hydrostatic pump in a sewer truck that uses high-pressure water jets and a powerful vacuum system to clean and maintain sewer systems.
  • Council members approved a $6,125 renewal of an annual contract with Medical Priority Consultants for licensing, training, implementation and maintenance of the Medical Priority Dispatch System. The system is used by dispatchers to interface with medical first responders and to assist with pre-arrival instructions for callers.
  • The council approved a request by the Northwest Homecoming Committee to hold the Northwest Missouri State University Homecoming parade on Oct. 25 with road closures from 7 a.m. until about 10:30 a.m.
  • Council members approved a liquor-by-the-drink Sunday license for The Pub.
  • The council approved a request by Justin Puckett, owner of Fatbackzz food trailer, to park his food truck on Third Street next to the courthouse parking lot on Friday and Saturday evenings from 7 p.m. to 1 a.m.

Leave a Comment